(1) Draft RFP filed May 2, 2022
(2) Community Meeting May 24, 2022
(3) Parties and Participants file Comments by June 2, 2022
(4) Community Meeting 2 July 14, 2022
(5) Technical Status Conference August 5, 2022
(6) Order 38735 Issued December 1, 2022
(7) Proposed Final RFP Filed December 22, 2022
(8) Final RFP issued by January 20, 2023
(9) Hawaiian Electric and Affiliate Proposal Due Date April 19, 2023 at 2:00 pm HST
(10) IPP Proposal Due Date April 20, 2023 at 2:00 pm HST
(11) Selection of Priority List July 6, 2023
(12) Hawaiian Electric and Affiliate BAFOs Due July 13, 2023
(13) IPP BAFOs Due July 14, 2023
(14) Selection of Final Award Group December 1, 2023
(15) IRS and Contract Negotiations Begin December 8, 2023

Stage 3 Maui Firm Renewable Generation RFP Schedule

Schedule as of 8/3/2023

Milestone Schedule Dates
(1) Request Pause - Firm Renewable Generation Portion April 12, 2023
(2) Order 39145 Issued April 14, 2023
(3) File revisions to the RFP, file information and analyses on the Waena Firm Site April 27, 2023
(4) Waena Firm Site – Site Visit May 4, 2023
(5) PUC Approval of RFP revisions May 11, 2023
(6) Filing of the Final Revised Maui Stage 3 RFP - Firm Renewable Generation Portion May 16, 2023
(7) Opening of the Final Revised Maui Stage 3 RFP – Firm Renewable Generation Portion May 19, 2023
(8) Hawaiian Electric and Affiliate Proposal Due Date August 16, 2023 at 2:00 pm HST
(9) IPP Proposal Due Date August 17, 2023 at 2:00 pm HST
(10) Selection of Priority List October 9, 2023
(11) Hawaiian Electric and Affiliate BAFOs Due October 16, 2023
(12) IPP BAFOs Due October 17, 2023
(13) Selection of Final Award Group January 23, 2024