Stage 3 Maui RFP Schedules
Stage 3 Maui Renewable Dispatchable Generation RFP Schedule
Schedule as of 10/16/2023
Milestone | Schedule Dates |
---|---|
(1) Draft RFP filed | May 2, 2022 |
(2) Community Meeting | May 24, 2022 |
(3) Parties and Participants file Comments by | June 2, 2022 |
(4) Community Meeting 2 | July 14, 2022 |
(5) Technical Status Conference | August 5, 2022 |
(6) Order 38735 Issued | December 1, 2022 |
(7) Proposed Final RFP Filed | December 22, 2022 |
(8) Final RFP issued by | January 20, 2023 |
(9) Hawaiian Electric and Affiliate Proposal Due Date | April 19, 2023 at 2:00 pm HST |
(10) IPP Proposal Due Date | April 20, 2023 at 2:00 pm HST |
(11) Selection of Priority List | July 6, 2023 |
(12) Hawaiian Electric and Affiliate BAFOs Due | July 13, 2023 |
(13) IPP BAFOs Due | July 14, 2023 |
(14) Selection of Final Award Group | December 1, 2023 |
(15) IRS and Contract Negotiations Begin | December 8, 2023 |
Stage 3 Maui Firm Renewable Generation RFP Schedule
Schedule as of 8/3/2023
Milestone | Schedule Dates |
---|---|
(1) Request Pause - Firm Renewable Generation Portion | April 12, 2023 |
(2) Order 39145 Issued | April 14, 2023 |
(3) File revisions to the RFP, file information and analyses on the Waena Firm Site | April 27, 2023 |
(4) Waena Firm Site – Site Visit | May 4, 2023 |
(5) PUC Approval of RFP revisions | May 11, 2023 |
(6) Filing of the Final Revised Maui Stage 3 RFP - Firm Renewable Generation Portion | May 16, 2023 |
(7) Opening of the Final Revised Maui Stage 3 RFP – Firm Renewable Generation Portion | May 19, 2023 |
(8) Hawaiian Electric and Affiliate Proposal Due Date | August 16, 2023 at 2:00 pm HST |
(9) IPP Proposal Due Date | August 17, 2023 at 2:00 pm HST |
(10) Selection of Priority List | October 9, 2023 |
(11) Hawaiian Electric and Affiliate BAFOs Due | October 16, 2023 |
(12) IPP BAFOs Due | October 17, 2023 |
(13) Selection of Final Award Group | January 23, 2024 |
(14) IRS and Contract Negotiations Begin | January 30, 2024 |