Selling Power to the Utility

CBRE LMI RFP Schedule

Proposed Schedule as of February 23, 2022

Milestone Schedule Dates
(1) Draft RFP filed July 9, 2020
(2) Technical Conference July 29, 2020
(3) Parties and Participants file Comments by August 12, 2020
(4) Proposed Final RFP filed September 8, 2020
(5) Updated RFP Draft filed Per Order 37592 March 30, 2021
(6) Parties and Participants file Comments by April 14, 2021
(7) Proposed Final RFP filed per Order 37879 August 25, 2021
(8) Proposed Final RFP filed per Order 38217 February 23, 2022
(9) Final RFP is Issued March 17, 2022
(10) IPP and Affiliate Proposal Due Date May 17, 2022 at 2:00 pm HST
(11) Priority List selected July 26, 2022
(12) BAFOs due August 2, 2021
(13) Final Award Group selected November 15, 2022
(14) Contract Negotiations Start November 22, 2022