Selling Power to the Utility

Grid Services Maui RFP 4 Schedule

Proposed Schedule as of August 25, 2023

Milestone Schedule Dates
(1) RFP issued February 1, 2023
(2) Questions due from Bidders June 30, 2023
(3) Response to Questions issued July 21, 2023
(4) Proposals Due December 1, 2023 at 5:00 pm HST
(5) Selection of Short List January 12, 2024
(6) Best and Final Offer Due January 26, 2024 at 5:00 pm HST
(7) Selection of Final Award Group February 9, 2024
(8) Contract Negotiations Start February 12, 2024
(9) Contract Executed and Filed (estimated) April 2024
(10) PUC Approval (estimated) November 2024
(11) Commercial Operations Date June 30, 2026