Selling Power to the Utility
Grid Services Maui RFP 4 Schedule
Proposed Schedule as of August 25, 2023
Milestone | Schedule Dates |
---|---|
(1) RFP issued | February 1, 2023 |
(2) Questions due from Bidders | June 30, 2023 |
(3) Response to Questions issued | July 21, 2023 |
(4) Proposals Due | December 1, 2023 at 5:00 pm HST |
(5) Selection of Short List | January 12, 2024 |
(6) Best and Final Offer Due | January 26, 2024 at 5:00 pm HST |
(7) Selection of Final Award Group | February 9, 2024 |
(8) Contract Negotiations Start | February 12, 2024 |
(9) Contract Executed and Filed (estimated) | April 2024 |
(10) PUC Approval (estimated) | November 2024 |
(11) Commercial Operations Date | June 30, 2026 |