Stage 3 Hawaii RFP Schedule
Schedule as of 9/27/2023
Milestone | Schedule Dates |
---|---|
(1) Draft RFP filed | October 15, 2021 |
(2) Community Meeting | October 28, 2021 |
(3) PUC Review and Further Direction | January 20, 2022 |
(4) Company filed 2nd Draft | March 18, 2022 |
(5) Technical Conference | April 14, 2022 |
(6) Company filed 3rd Draft | May 31, 2022 |
(7) Order 38653 | October 17, 2022 |
(8) Proposed Final RFP filed | November 7, 2022 |
(9) RFP is Issued | November 21, 2022 |
(10) Order 38865 | February 17, 2023 |
(11) Hawaiian Electric and Affiliate Proposal Due | April 19, 2023 at 2:00 pm HST |
(12) IPP Proposal Due Date | April 20, 2023 at 2:00 pm HST |
(13) Selection of Priority List | July 6, 2023 |
(14) Hawaiian Electric and Affiliate BAFOs Due | July 13, 2023 |
(15) IPP BAFOs Due | July 14, 2023 |
(16) Selection of Final Award Group | December 1, 2023 |
(17) IRS and Contract Negotiations Begin | December 8, 2023 |