Selling Power to the Utility
Stage 3 Oahu RFP Schedule
Schedule as of 9/27/2023
Milestone | Schedule Dates |
---|---|
(1) Draft RFP filed | May 2, 2022 |
(2) Community Meeting | May 24, 2022 |
(3) Parties and Participants file Comments by | June 2, 2022 |
(4) Community Meeting 2 | July 14, 2022 |
(5) Technical Status Conference | August 5, 2022 |
(6) Order 38735 Issued | December 1, 2022 |
(7) Proposed Final RFP Filed | December 22, 2022 |
(8) Final RFP issued by | January 20, 2023 |
(9) Hawaiian Electric and Affiliate Proposal Due Date | April 19, 2023 at 2:00 pm HST |
(10) IPP Proposal Due Date | April 20, 2023 at 2:00 pm HST |
(11) Selection of Priority List | July 6, 2023 |
(12) Hawaiian Electric and Affiliate BAFOs Due | July 13, 2023 |
(13) IPP BAFOs Due | July 14, 2023 |
(14) Selection of Final Award Group | December 1, 2023 |
(15) IRS and Contract Negotiations Begin | December 8, 2023 |