CBRE Molokai RFP Schedule
Proposed Schedule as of February 14, 2022
Milestone | Schedule Dates |
---|---|
(1) Draft RFP filed | July 9, 2020 |
(2) Technical Status Conference | July 29, 2020 |
(3) Parties and Participants file Comments by | August 12, 2020 |
(4) Proposed Final RFP filed | September 8, 2020 |
(5) Updated RFP Draft filed Per Order 37592 | March 30, 2021 |
(6) Parties and Participants file Comments by | April 14, 2021 |
(7) Proposed Updated RFP filed per Order 37879 | August 31, 2021 |
(8) Proposed Final RFP filed per Order 38038 | November 4, 2021 |
(9) Final RFP is Issued | November 22, 2021 |
(10) IPP Proposal Due Date | March 1, 2022 at 2:00 pm HST* |
(11) Selection of Priority List | May 4, 2022 |
(12) BAFOs due | May 11, 2022 |
(13) Selection of Final Award Group | August 24, 2022 |
(14) Contract Execution Start | August 31, 2022 |